Contingency plan
Contingency plans are plans than could be enacted to mitigate project risks identified during risk assessment, if those risks increase or materialise. That is, they are alternative courses of action devised to cope with project risks.
Predictable risks that could be mitigated with forward planning might include:
- Non-delivery of materials. An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed
- Lack of available work force. This could be tackled by the provision of a site labour camp or by overseas recruitment.
- Lack of plant and equipment availability (or plant failure or access to spare parts). Plant such as piling rigs and spares could be ordered during the design stages prior to contractor involvement.
- Illness. This could be mitigated by insurance cover for key personnel.
- The risk of obtaining planning permission or other statutory approvals. This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority.
- Information and communications technology failure. This might be mitigated by duplicating facilities, establishing back-up procedures and providing uninterrupted power supplies.
- Failure of power or water supply. This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
NB Functional Standards Common Glossary, published by the Cabinet Office, defines contingency planning/ plans as: ‘A course of action and resulting document(s) that prepares the organisation to respond effectively to future significant events, incidents and risks.’
[edit] Related articles on Designing Buildings
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.